Premier Inn, Ipswich

  • Project: Premier Inn Ipswich
  • Type: Hotel
  • Customer: ISG Ipswich
  • Client: Premier Inns
  • Completion Date: October 2012

Project Background

Kingspan Timber Solution has worked with ISG on a number of challenging contracts. We were asked to consider a timber frame construction for this 6 storey hotel and restaurant.

The Challenge

The ground floor of the hotel was a traditional brick and block construction. We built the framework for the remaining floors off a podium transfer slab. ISG consulted us regarding the design for disproportionate collapse. They also required help with cost challenges within the project.

Quality Assured

As a company, we recognise a collective responsibility to protect the environment and optimise waste management. Through our design, manufacture and construction processes we minimise and where possible eliminate waste.

KTS offers a world class, flexible UK based manufacturing facility and is accredited to ISO 9001, ISO 14001 and OHSAS 18001 for quality management, environmental management and health and safety.

We are a CHAS and SMAS accredited worksafe contractor, employing only fully trained, CSCS and UKTFA (UK Timber Frame Association) accredited erectors.

All our timber is imported from fully sustainable PEFC (Programme for the Endorsement of Forest Certification) or FSC (Forest Stewardship Council) accredited sources.